Once your subdivision is approved, you have 20 business days to challenge any conditions you can't live with. After that the real work starts: engineering, site works, utility connections, fees and plan sealing, all before Titles Queensland issues your new titles. Here's every step in order for a typical small Brisbane subdivision, with the deadlines that catch people out.
Just got your approval? Send us your decision notice and we'll map out your steps, costs and timeframe. Send us your approval
Step 1: Read every condition in your decision notice (first 20 business days)
Your approval is a list of conditions, not a finish line. Read the decision notice and approved plans in full and work out what each condition requires, who does it and when.
This matters now because the clock is running. As the applicant you have 20 business days from the decision notice to appeal a condition. In that time you can also ask Council to reconsider conditions through change representations, which is often quicker and cheaper than going to court. Once the period ends, changing a condition means a formal change application.
Check your infrastructure charges notice at the same time. It has its own 20 business day appeal period.
Step 2: Note when your approval lapses
A subdivision approval doesn't last forever. Under the Planning Act, it usually lapses if the survey plan isn't lodged with Council within 4 years of the approval taking effect, unless your approval states a different period. Put the date in your calendar now. Extensions are possible but not guaranteed.
Step 3: Build your team and get quotes
Even a simple 1-into-2 subdivision usually needs:
-
a surveyor for set-out, the survey plan and as-constructed surveys
-
a civil engineer for sewer, water, stormwater and driveway designs
-
contractors for demolition, connections, crossovers, footpaths and landscaping
-
a solicitor if easements or covenants are required
-
specialists where conditions require them, such as an arborist or CCTV sewer inspections
Get quotes against the actual conditions, not a generic scope. Missing a condition at this stage is where most budget blowouts start.
Step 4: Get engineering and utility approvals
Many conditions need designs approved before work starts. Depending on your conditions, this can include:
-
Operational works approval from Council for things like stormwater, earthworks, roadworks or driveways.
-
An Urban Utilities Water Approval for new or altered water and sewer connections. Urban Utilities assesses the design, approves the works, and later inspects them.
-
Energex and NBN applications for power and telecommunications to the new lots.
Lodge these early. Their timeframes run in parallel and often set the pace for the whole project.
Step 5: Do the site works
With approvals in hand, contractors complete the works: demolition or house relocation, service connections, driveways and crossovers, footpaths, street trees and verge works. Many items need inspections and certificates along the way, so keep every document.
Step 6: Get your Urban Utilities Connection Certificate
Once the water and sewer works are finished and inspected, your engineer submits an as-constructed package to Urban Utilities. Urban Utilities then issues a Connection Certificate. Council won't seal your plan without it, and it must reference your current approval and stage.
Step 7: Pay infrastructure charges and bonds, and sign easements
Before plan sealing, you'll need to pay Council's infrastructure charges, any outstanding rates and the plan sealing fees. Some unfinished works can be bonded so sealing isn't held up. Easement documents must be signed and ready. See our guide to bonds, infrastructure charges and fees to pay before plan sealing.
Step 8: Lodge your plan sealing request
Your surveyor or town planner lodges the plan sealing request with Council. It includes the survey plan, Titles Queensland Form 18A, the Urban Utilities Connection Certificate, payment receipts and evidence that every condition has been met. Council aims to respond within 20 business days. If anything is missing, it asks for more information and the clock effectively restarts.
Council offers a pre-lodgement service, and accredited consultants can use its faster SealSMART stream. Our Plan Sealing Checklist lists every document Council looks for.
Step 9: Register with Titles Queensland (within 6 months)
Once Council seals the plan, it must be lodged with Titles Queensland for registration within 6 months. Your solicitor or surveyor lodges it with any easements and other documents. When it's registered, your new lots have their own titles and can be sold or financed separately.
Where projects get stuck
-
A condition was missed at the start, so works have to be redone.
-
Urban Utilities, Energex or NBN applications are lodged late.
-
Certificates and inspection records go missing, so plan sealing can't be lodged.
-
The approval lapses while the owner is busy with other things.
Every month of delay adds holding costs. That's why many owners hand the whole process to a project manager. See do you need a project manager for your subdivision?
How we help
We manage Brisbane subdivisions from development approval through to new titles. We review your conditions, build the team, lodge the engineering and utility applications, track every certificate, and handle plan sealing. You get one point of contact and regular updates instead of a dozen parties to chase. Find out more about our development project management and plan sealing services.
FAQs
How long after DA approval do you get new titles in Brisbane?
It depends on your conditions and how quickly the works and utility approvals move. Plan sealing alone has a 20 business day assessment period, and titles registration comes after that. The fastest projects are the ones where every application is lodged early and every certificate is ready when it's needed.
Can I change my conditions after approval?
Yes. Within 20 business days of the decision notice you can make change representations or appeal. After that, you'll need a change application to Council.
When do I pay infrastructure charges?
In Brisbane, infrastructure charges must be paid before Council will seal your survey plan.
What is plan sealing?
Plan sealing is Council endorsing your survey plan once every condition has been met. You need the sealed plan to register new titles with Titles Queensland.
How long is a subdivision approval valid?
Usually 4 years to lodge the survey plan with Council, unless the approval states a different period. You can apply to extend it before it lapses.
Do I need a project manager after DA approval?
Not always, but it helps if this is your first subdivision, you work full time, or you're paying holding costs on a loan.