Plan Sealing Checklist: Every Document Brisbane City Council Needs

Brisbane Town Planners ·

To get a survey plan sealed in Brisbane, you need to show council that every condition of your development approval has been met. In practice that means an endorsed-ready survey plan, evidence for each condition, certificates from your engineers and service providers, and proof that fees, charges and bonds are paid. Missing any one of these is the most common reason titles are delayed.

This checklist covers what is usually needed for subdivisions and townhouse projects in Brisbane. Your own decision notice is the final word, so check it line by line.

Want us to check your conditions? Send us your DA number and we'll tell you what's still outstanding. Get help with plan sealing

1. The survey plan

  • Survey plan prepared by a registered surveyor after the new lots are pegged, matching the approved layout
  • Owner's consent to the plan, signed by every registered owner
  • Easement documents for any private access, drainage or flood easements in the conditions
  • Community Management Statement, if the development is a community titles scheme (townhouses, shared driveways)

2. Your approval documents

  • The decision notice, approved plans and the infrastructure charges notice
  • Any later change approvals, and the currency period end date (plan sealing must happen before it lapses)
  • Operational works approvals for engineering, landscaping, vegetation or rehabilitation works, if conditioned

3. Evidence for every condition

Council wants to see how each condition was met. The easiest way is a compliance table: every condition, how it was met, and the document that proves it.

  • A compliance statement or table covering each condition
  • Photos or inspection records for completed works, such as driveways, footpaths and landscaping
  • Evidence that existing structures were removed or relocated, if required

4. Engineering and service certificates

  • RPEQ-certified as-constructed stormwater plans and compliance certificates
  • Urban Utilities connection certificates for water and sewer
  • Energex certificate for electricity supply, including property pole certification if needed
  • NBN provisioning agreement
  • QBCC Form 4 from the plumber if an old sewer connection was capped or moved
  • Landscape design and works certificates, if landscaping is conditioned
  • Arborist or ecologist compliance certificates, if trees or vegetation are conditioned
  • Council on-maintenance acceptance for roadworks, stormwater or new street trees
  • Building inspection certificate (Form 16), if dwellings must reach a set stage before sealing

5. Money matters

  • Council infrastructure charges paid, with a zero-balance statement
  • Urban Utilities infrastructure charges paid
  • Maintenance or uncompleted works bonds lodged
  • Council rates paid up to date, with no balance outstanding
  • Plan sealing application fee

6. Other parties

  • Mortgagee consent, if the land is mortgaged
  • Solicitor engaged to lodge the sealed plan with Titles Queensland

What council checks at the site inspection

Paperwork is only half of it. Before sealing, council usually inspects the site and the verge. These are the items that most often fail:

  • Verge and turf. Every disturbed area of verge needs new turf, laid flush with footpaths, driveways and service lids. The verge should fall towards the road at about 1 in 50.
  • Footpaths. Where a new footpath meets an existing one of a different width, it needs a gradual taper, kept within your own frontage.
  • Kerb and channel. Damaged or redundant sections, such as an old crossover or stormwater outlet, must be saw cut and replaced as one piece, kerb and channel together.
  • Driveway crossovers. These must match the type and standard drawing in your conditions. Grid crossovers and decorative finishes are usually not accepted without council's written approval.
  • Street trees. Protection fencing must go up before works start, and existing street trees must be healthy at the end.
  • Site leftovers. Temporary fencing and sediment fences must sit inside the property, not on the verge. The temporary site entry must be removed and the verge returned to turf.
  • Road damage. Any damage to the road, line markings or kerb from construction vehicles must be repaired.

A failed inspection means fixing the work and booking another inspection. It's the most avoidable delay in the whole process.

Why plan sealing gets delayed

Most delays aren't caused by council being slow. They happen because something on this list is discovered missing at the end. A certificate the engineer never issued. A condition nobody read until the works were finished. A bond nobody paid.

The fix is to plan for sealing from day one. Map each condition to a stage of the project and collect the evidence as you go. That's exactly what a project manager does.

For more on the common causes, read Plan Sealing in Brisbane.

FAQs

Who lodges the plan sealing application?

Usually the town planner or surveyor, on the owner's behalf. Council then reviews the survey plan against the approval conditions.

How long does Brisbane City Council take to seal a plan?

If the application is complete, council assessment is often a matter of weeks. Missing evidence restarts the clock, which is why the checklist matters.

Does this checklist apply outside Brisbane?

The principles are the same in Logan, Ipswich, Moreton Bay, Redlands and the Gold Coast, but each council has its own forms and requirements.

Can I do plan sealing myself?

You can, but it means chasing every consultant and matching every condition yourself. Most owners use a planner to avoid going back and forth with council.

Close to finishing?

Send us your DA number and we'll check your conditions against this list. We'll tell you exactly what's left before your titles can be issued.