Before Brisbane City Council will seal your survey plan, you must pay Council's infrastructure charges, any outstanding rates, and the plan sealing and compliance fees. You also need an Urban Utilities connection certificate showing its water and sewer charges have been paid.
For a typical small subdivision, the infrastructure charges are by far the biggest item. Council's share is $18,793.33 for each new residential lot under the charges that started on 1 July 2026. Urban Utilities' water and sewer charge is usually a similar amount, so allow around $37,000 to $38,000 per new lot in total. Bonds can add more if you want the plan sealed before every piece of work is finished.
None of this is a surprise if you plan for it. The problem is that many owners only find out the full amount when the invoices arrive, right at the end of a long project. This guide sets out what you will pay, when, and how to avoid being caught short.
Want to know what your subdivision will cost to seal? Send us the address and your approval number. We'll tell you what's owing and what's still to do before Council will sign off.
What has to be paid before Council seals the plan?
Council's plan sealing page lists what must be paid before it will endorse a survey plan:
- Council's infrastructure charges
- any outstanding Council rates
- the application and compliance fees for the sealing request.
Council also needs an Urban Utilities connection certificate that references your current approval. The certificate states whether Urban Utilities' infrastructure charges have been paid. If anything is still owing, Council won't accept it for plan sealing.
Once everything is in and paid, Council's stated timeframe to seal the plan is 20 business days.
Infrastructure charges: the biggest cost
Infrastructure charges pay for the trunk networks your new lots will use: roads, parks, stormwater, water and sewer. In Brisbane they come in two parts.
Council's charge. Under the Brisbane Infrastructure Charges Resolution (No. 15) 2026, which started on 1 July 2026, Council's adopted charge for reconfiguring a lot is $18,793.33 per lot. This covers transport, parks and community land, and stormwater.
Urban Utilities' charge. Water supply and sewerage charges are levied separately by Urban Utilities. In our experience the amount is usually similar to Council's, so the two together come to roughly double Council's figure. They must be paid in full before plan sealing, because Council needs a connection certificate showing nothing is owing.
The exact amount for your project is in the infrastructure charges notice that came with your approval. Check that notice before you budget, not the headline rate.
Do I pay for every lot?
No. You pay for the extra demand you create. Council gives a credit for an existing lot, so splitting one lot into two generally means paying for one additional lot, not two.
The credit only applies where there is evidence of the existing lot's demand. Your infrastructure charges notice shows how the credit was worked out.
Why the amount can be higher than your notice
For approvals issued from 23 June 2023, Council indexes infrastructure charges. The charge rises from the day it was levied to the day you pay, using the Producer Price Index.
If your approval is a few years old, expect the invoice to be higher than the figure on the notice. The increase is capped by the State Government's maximum charge.
Council's plan sealing and compliance fees (2026-27)
Council sets its development fees in points, at $150 a point for 2026-27. The fees you are most likely to meet at plan sealing are:
- Request to approve a plan of subdivision: $600 per request, plus $450 per lot on the survey plan
- Compliance and inspection for a reconfiguration of 1-10 lots: $1,500 per lot
- Compliance and inspection for a boundary realignment: $1,050 per approval
- Re-submission or re-endorsement of a survey plan: $600
- Additional site inspection, if work is incomplete: $600 per inspection
- Community title scheme endorsement, up to 3 units: $2,700, plus $750 per extra unit
- Community management statement endorsement: $1,350 each
The last three only apply in some projects. Re-submission and re-inspection fees are avoidable if the request goes in complete.
Bonds for uncompleted work
Sometimes a small item of work is not finished when everything else is ready, such as landscaping or a footpath. Council may agree to seal the plan if you lodge a bond to cover that work.
Bonding has its own costs in 2026-27:
- Request to accept a bond for uncompleted work: $3,000 per bond component
- Minimum bond amount: $25,000
- Request to reduce or release a bond: $1,950 per request
- Preparing a deed of agreement: $6,750 per deed
With a $25,000 minimum and fees on top, it's worth weighing the cost of bonding against the cost of waiting for the work to finish.
Other costs to allow for
- Rates. Council rates on the parent lot must be up to date before sealing.
- Consultants. Your surveyor prepares the survey plan, and engineers or other consultants may need to certify works.
- Titles Queensland. After sealing, the plan must be lodged for registration, which has its own fees.
How to avoid surprises at the end
- Read your infrastructure charges notice when the approval arrives. Note the amount, the credit and the date it was levied.
- Budget for indexation if the project will take more than a few months.
- Talk to Urban Utilities early and pay its charges in time, so the connection certificate shows nothing owing.
- Decide early whether bonding makes sense, rather than at the last minute.
- Lodge a complete sealing request to avoid re-submission and re-inspection fees.
Our Plan Sealing Checklist for Brisbane lists every document Council will ask for. For the common causes of delay, read why plan sealing gets delayed in Brisbane.
Frequently asked questions
When do I pay infrastructure charges for a subdivision in Brisbane?
Council's charges are paid before Council seals the survey plan. Urban Utilities' water and sewer charges must also be paid, because Council needs a connection certificate showing nothing is owing.
How much are infrastructure charges per lot in Brisbane?
Council's adopted charge is $18,793.33 per lot from 1 July 2026. Urban Utilities charges separately for water and sewer, usually a similar amount, so allow around $37,000 to $38,000 per new lot in total. Your infrastructure charges notice shows the exact amount for your approval.
Do I pay infrastructure charges on the existing lot?
Generally no. Council gives a credit for the existing lot, so a one-into-two subdivision usually pays for one additional lot.
Why is my invoice higher than my infrastructure charges notice?
For approvals from 23 June 2023, charges are indexed from the date they were levied until they are paid. The longer the gap, the bigger the increase.
Can I get my plan sealed before all the works are finished?
Sometimes. Council may accept a bond for uncompleted work. In 2026-27 the minimum bond is $25,000, and the request fee is $3,000 per bond component.
How long does plan sealing take once everything is paid?
Council's stated timeframe is 20 business days after the lodgement fee is paid, if the request is complete.
Need help getting to plan sealing?
Brisbane Town Planners and Project Management works through the conditions, coordinates the consultants and Urban Utilities, and puts together a complete sealing request. See our plan sealing service, or our development project management if you want one team from approval to titles.
Send us the address and your approval number and we'll tell you what's left to do.
This article is general information based on Brisbane City Council's 2026-27 fees and charges. It isn't advice for your specific project. Check your own approval and infrastructure charges notice before you budget.