Short answer: a straightforward 1-into-2 subdivision in Brisbane usually costs $100,000 to $150,000 all-in. Complex sites, with demolition, a long driveway, underground power or retaining walls, can pass $200,000. The single biggest cost is the infrastructure charge, about $38,000 for the new lot.
Those figures cover everything from the first survey to new titles: council fees, consultants, service connections, site works and charges. Here's where the money goes, stage by stage.
Subdivision costs at a glance
| Stage | Typical cost (1 into 2) |
|---|---|
| 1. Development application | $12,000 – $25,000 |
| 2. Services and site works | $35,000 – $60,000 (more for complex sites) |
| 3. Infrastructure charges | about $38,000 per new lot |
| 4. Plan sealing and titles | $8,000 – $10,000 |
| Total | $100,000 – $150,000 |
All figures include GST and are typical estimates for Brisbane City Council in 2026–27. Council fees are reviewed every July and infrastructure charges are indexed, so check current figures for your own project.
Stage 1: The development application ($12,000 – $25,000)
In Queensland, subdividing is called reconfiguring a lot, and in Brisbane it needs a development application (DA) to Council. Typical costs:
- Contour and detail survey, and subdivision proposal plan: about $3,300
- Town planning report, code assessment and lodgement: $4,000 – $5,500
- Council application fee (2 lots, code assessment): $4,500
- Impact assessment fee, if your proposal doesn't comply with the planning scheme: an extra $3,900, plus about $1,500 for public notification
- State referral (SARA), for example next to a railway or state road: about $2,000 – $3,500 in State fees, plus preparing the referral
- Specialist reports, if needed: stormwater, arborist, bushfire or ecology reports, typically $1,500 – $5,000 each
A simple, code-assessable 1-into-2 sits at the lower end. Overlays, referrals and non-compliance push it up. See How much does a development application cost in Brisbane? for more on DA fees.
Stage 2: Services and site works ($35,000 – $60,000+)
Once the DA is approved, the conditions tell you what has to be built before Council will seal the plan. This is where costs vary the most from block to block.
Water and sewer (Urban Utilities)
- New sewer connection: about $7,000
- New water connection: about $8,000
Electricity and telecommunications
- Overhead power with a private pole: $1,500 – $5,000
- Underground power with a new pillar: about $18,000
- Energex supply certificate: about $4,200
- NBN certificate and conduits: $1,200 – $3,000
Engineering and site works
- Civil engineer design and sign-off: about $12,000
- Earthworks and levelling: about $5,500
- Sediment fencing and turf to the footpath: about $6,000
- Street tree fee and tree protection: $1,000 – $2,000
- Driveway and footpath works: up to $25,000 for a long shared or battle-axe driveway
- Retaining walls: around $500 per square metre, if needed
- New boundary fencing: around $175 per linear metre
- Demolition, if the existing house is removed: $30,000 – $40,000
Survey and easements
- Subdivision survey and final plan: about $4,500
- Easements (for example access or services), prepared by a solicitor: $1,500 – $3,000, plus Council or Urban Utilities fees of about $900 – $1,800 if a stormwater or sewer easement is needed
Keeping the existing house, having sewer and water close to the new lot, and using overhead power keep this stage at the lower end. Demolition, a long rear driveway, underground power and a sloping block push it up quickly.
Stage 3: Infrastructure charges (about $38,000 per new lot)
Infrastructure charges are the largest single cost in most Brisbane subdivisions. They're paid for each additional lot you create, so a 1-into-2 subdivision pays for one lot, because the existing lot already has a credit.
The charge has two parts:
- Brisbane City Council (roads, parks, stormwater): $18,793 per lot under the current charges resolution
- Urban Utilities (water and sewer): a similar amount again
Together that's about $38,000 per new lot in 2026–27. The charge is indexed, so the amount on your invoice depends on when you pay, and it must be paid before Council will seal the survey plan.
Stage 4: Plan sealing and new titles ($8,000 – $10,000)
The last step is getting Council to endorse (seal) the survey plan, then registering the new titles.
- Preparing the plan sealing application and compliance report: about $2,500
- Council plan sealing fee (2 lots): $1,500
- Council compliance assessment fee (2 lots): $3,000
- Titles Queensland lodgement fees: about $1,200
- Preparing and lodging title documents: about $500
See our plan sealing page for what Council checks at this stage.
Worked example: a 1-into-2 subdivision keeping the existing house
An 810 m² block in a low-medium density zone, split into two lots. The house stays on the front lot, services are close by, and power is overhead.
| Stage | Estimate |
|---|---|
| Development application (survey, planning report, Council fee) | $12,090 |
| Services and site works (sewer, water, power, NBN, engineer, site works, survey, easements) | $49,410 |
| Infrastructure charges (1 new lot) | $38,030 |
| Plan sealing (preparation, Council fees) | $7,030 |
| Titles | $1,695 |
| Total | $108,255 |
Add demolition, a 25-metre driveway, underground power and some retaining walls, and the same subdivision can cost well over $200,000.
What pushes subdivision costs up
- Demolishing the existing house rather than keeping it
- Battle-axe or rear lots that need a long driveway and services run down the side
- Underground power, or upgrades Energex requires before it will supply the new lot
- Sewer or water mains that need extending to reach the new lot
- Flood, bushfire or other overlays that require filling, reports or design changes
- Impact assessment or State referral, which add fees, time and public notification
- Sloping blocks that need earthworks and retaining walls
- Significant trees that must be kept or assessed
How to keep subdivision costs down
- Check your block before you start. Zone, minimum lot size, overlays and where the services run decide most of your cost. Our guide Can I subdivide my property in Brisbane? covers what to look for.
- Design to comply with City Plan. A code-assessable application avoids impact assessment fees, public notification and months of delay.
- Get services located early. Knowing where sewer, water and power are before the layout is fixed avoids expensive extensions later.
- Get trade quotes early. Demolition, driveways and electrical works vary a lot between contractors.
- Manage the conditions as one project. Most blowouts happen after approval, when conditions, contractors and certificates aren't coordinated. See what happens after your DA is approved.
How long does it take?
A straightforward code-assessable subdivision usually takes 3 to 4 months to get approved. Construction of services and plan sealing then usually adds another 3 to 9 months, depending on contractors and Energex and Urban Utilities timeframes. See How long does a development application take in Brisbane?
Frequently asked questions
How much does a 1-into-2 subdivision cost in Brisbane?
Usually $100,000 to $150,000 all-in for a straightforward site, including about $38,000 in infrastructure charges. Complex sites can pass $200,000.
What is the biggest cost when subdividing in Brisbane?
Infrastructure charges, at about $38,000 for each new lot in 2026–27, made up of Brisbane City Council's and Urban Utilities' charges.
Do I pay infrastructure charges on both lots?
No. Charges apply to each additional lot. In a 1-into-2 subdivision, the existing lot gets a credit, so you pay for one new lot.
How much is the Council application fee to subdivide?
For 2026–27, Brisbane City Council charges $4,500 for a code-assessable application creating up to two lots. Impact assessment adds $3,900.
Is subdividing worth it?
It depends on the value of the new lot compared with the total cost and the time involved. On many Brisbane blocks, a new lot is worth well above $150,000, but the numbers should be checked for your site before you spend money on plans.